Brownsville Large-Scale Seawater Desalination Pilot Plant Study
Project Summary
As part of the state's Seawater Desalination Initiative, the Brownsville Public Utilities Board is seeking to develop the state's first large-scale seawater desalination plant (View Schematics). A 2004 Seawater Desalination Feasibility study provided recommendation for developing such a facility at the Brownsville Ship Channel. The goal of the current 12-month pilot plant study is to collect source water quality data, and assess and optimize the desalination processes recommended in the feasibility study.
- TWDB Contract Manager:
 - Jorge Arroyo
 - Funding Recipient:
 - Brownsville Public Utilities Board
 - Project Administrator:
 - Brownsville Public Utilities Board
 - Contractors:
 - NRS Consulting Engineers
 - Project Start Date:
 - July 18, 2006
 - Project Completion Date:
 - December 2008
 - Total Project Cost:
 - $2,225,056.83
 - TWDB Share of Project Cost:
 - $1,340,000
 - Benefits:
 - The pilot plant study will provide reliable, site-specific source data to support the design, funding and construction of a large-scale seawater desalination plant.
 
Project Details
Participants
Project Sponsor:
Texas Water Development Board
				Jorge Arroyo, P.E. - Contract Manager
				1700 N. Congress Avenue
				Austin, TX 78711
				512-475-3003
Funding Recipient:
Brownsville Public Utilities Board
				Mr. John S. Bruciak - CEO and General Manager
				1425 Robinhood Drive
				P.O. Box 3270
				Brownsville, TX 78523-3270
				800-869-2922
Project Manager:
NRS Consulting Engineers
				Mr. Bill Norris - Principal
				1222 E. Tyler, Suite C
				P.O. Box 2544
				Harlingen, TX 78551
				956-423-7409
Project Engineer:
NRS Consulting Engineers
				Mr. Bill Norris - Principal
				1222 E. Tyler, Suite C
				P.O. Box 2544
				Harlingen, TX 78551
				956-423-7409
Final Report
Final Pilot Study Report: Texas Seawater Desalination Demonstration Project (10.78 MB)
Project Milestones
| Event | Date | 
|---|---|
| Statement of Interest received by TWDB | March 9, 2006 | 
| TWDB Board authorizes contract negotiations | April 17, 2006 | 
| Contract executed (official start of project) | July 18, 2006 | 
| Project engineer selected by Brownsville PUB | February 13, 2006 | 
| Pilot plant start-up date | February 27, 2007 | 
Photographs
Courtesy of Brownsville Public Utilities Board/NRS Engineers - November/December 2006