Project Summary:
The purpose of this project was to provide directly measured rock parameters that are correlated with geophysical logs for various aquifers studied or to be studied by BRACS. Core data was analyzed for the Maverick Basin (seven cores), Woodbine (four cores), Capitan Reef Complex (one core) and Edwards Balcones Fault Zone (one core). Measured rock parameters included bulk mineralogy, porosity, permeability, cementation or “m”-factor and nuclear magnetic resonance for each core plug interval.
- TWDB Contract Manager:
- Kristie Laughlin, P.G.
- Funding Recipient:
- LRE Water, LLC
- Contract Number:
- 2348302708
- Project Manager:
- Allan R. Standen, P.G.
- Project Start Date:
- May 2023
- Project Completed:
- August 2024
- Total Project Cost:
- $175,000
- TWDB Share of Project Cost:
- $175,000
Final Report and Core Data
- TWDB Contracted Report 2348302708 - Core Analyses for Various Aquifers
- Appendix A, Core Geophysical Logs
- Appendix B, Core Lithologic Decriptions
- Appendix C, Core Photos JPG
- Appendix D, Core Lab's Analyses Results
Report citation: Standen, A.R., Swientek, L., Murphy, S., 2024, Final Report: Core Analyses for Various Aquifers: LRE Water, LLC, Contract report 2348302708 to the Texas Water Development Board, 47 p.