WEBVTT

00:04.710 --> 00:04.814
RON ELLIS: OK.

00:04.814 --> 00:05.644
It's 10:01.

00:05.644 --> 00:07.440
Let's go ahead and get started.

00:08.160 --> 00:09.150
Good morning again.

00:10.020 --> 00:12.390
Welcome to our webinar on regional water

00:12.390 --> 00:14.190
planning contracts and payments.

00:14.820 --> 00:18.141
I'm Ron Ellis with
the regional water planning staff.

00:18.141 --> 00:21.460
I along with Lisa Farrell whose
team leader for contract

00:21.460 --> 00:23.940
payments will be giving this
morning's presentation.

00:25.220 --> 00:27.770
Please note that we're
recording the presentation.

00:27.770 --> 00:33.095
And we plan to post a link
on it on our website.

00:33.095 --> 00:36.512
So, you all can access it as
a resource later if needed.

00:36.512 --> 00:43.350
So, this presentation is intended to give

00:43.350 --> 00:45.450
a general overview of the regional

00:45.450 --> 00:47.700
water planning payment request process

00:48.390 --> 00:51.659
and related contracting requirements.

00:52.200 --> 00:56.250
It's not intended to be
a comprehensive reference document.

00:57.090 --> 00:59.670
For full details and guidance,

01:00.390 --> 01:03.690
please refer to the regional
water planning contract document

01:03.690 --> 01:06.600
that's been executed
between the planning group

01:06.600 --> 01:11.030
sponsor and the TWDB in your region.

01:11.030 --> 01:18.600
So, your planner for your region
is also your contract manager

01:19.200 --> 01:22.920
and your first contact for
contract-related matters.

01:22.920 --> 01:26.580
Our contact information is
presented on this slide.

01:27.830 --> 01:31.550
We in regional water planning
had been fortunate to not

01:31.550 --> 01:34.320
have a lot of turnover
recently in these positions.

01:34.320 --> 01:36.590
So, you should know us pretty well.

01:37.580 --> 01:41.044
Please don't hesitate to reach out to us.

01:41.044 --> 01:47.510
If you are new to the process and you
don't know your planner very well,

01:47.510 --> 01:52.160
please feel free to reach
out between meetings

01:52.160 --> 01:54.612
or get to know them at a meeting.

01:54.612 --> 01:58.270
SPEAKER: Or so sometimes just sit down and visit

01:58.270 --> 02:01.860
but I think we're in pretty good shape.

02:01.860 --> 02:05.500
RON ELLIS: Can everybody please mute.

02:05.500 --> 02:06.274
Thanks.

02:06.274 --> 02:07.822
So, yeah.

02:07.822 --> 02:11.770
Please don't hesitate to reach out
to your planner if you've got

02:11.770 --> 02:14.290
questions about the planning
process or about your contract.

02:16.419 --> 02:20.713
I'll let Lisa introduce
the contract staff.

02:20.713 --> 02:24.222
CAMERON TURNER: I'll actually do so.

02:24.222 --> 02:26.100
Hey, Ron.

02:26.100 --> 02:31.142
I'm Cameron Turner, director of
procurement and contract services.

02:31.142 --> 02:34.120
And with us we've got Stephen Ross,

02:34.120 --> 02:38.950
who is a team lead on our
contract development team.

02:39.460 --> 02:43.630
And so your items that require
some sort of contract

02:43.630 --> 02:47.200
action in terms of amendments,
budget revisions,

02:47.200 --> 02:52.570
subcontract approvals would go
through our contracts inbox as well

02:52.570 --> 02:56.554
as your assigned contract manager,
the planner that Ron mentioned.

02:56.554 --> 02:59.750
And Stephen and his team
will help process those.

02:59.750 --> 03:04.720
And then Lisa Farrell is our
contract specialist on the team

03:04.720 --> 03:09.790
lead for contract payments,
making sure you'll get paid.

03:10.060 --> 03:13.143
And so with that I don't
if know if Stephen, Lisa.

03:13.143 --> 03:14.950
Stephen if you got anything to say.

03:14.950 --> 03:18.730
I know Lisa's got a good
bit to say to help give

03:18.730 --> 03:21.310
folks some guidance on
processing payments.

03:21.760 --> 03:24.790
But anytime that you have
any questions as well that

03:25.120 --> 03:29.230
your contract manager
can answer, feel free.

03:29.540 --> 03:35.715
I have open door policy and would
love to chat with you all as well.

03:35.715 --> 03:37.608
STEPHEN ROSS: Nothing for me.

03:37.608 --> 03:43.570
I'll turn it over to Lisa and let her
carry forward with the discussion.

03:43.570 --> 03:45.517
LISA FARRELL: Thanks, Cameron and Stephen.

03:45.517 --> 03:46.260
I appreciate it.

03:46.290 --> 03:47.520
Hi, I'm Lisa Farrell.

03:47.670 --> 03:49.170
I'm a contract specialist here.

03:49.170 --> 03:51.330
As Cameron mentioned, I'm the team lead

03:51.330 --> 03:54.140
now for TWDB's contract payments.

03:54.140 --> 03:57.120
So, my introduction to
regional water planning

03:57.120 --> 03:58.950
was when I started with this agency

03:58.950 --> 04:02.610
six and a half years ago and that
was at the end of the fourth cycle.

04:02.610 --> 04:04.260
And yes, I'm still here.

04:04.260 --> 04:05.800
So, happy to be here.

04:05.800 --> 04:08.520
I recognize a lot of names
here that are online.

04:08.520 --> 04:13.215
If you wouldn't mind, hey, use
the reactions here and give us a thumbs

04:13.215 --> 04:17.354
up if we've actually have
communicated by phone or by email.

04:17.354 --> 04:20.460
Hopefully, I won't see any unhappy emojis.

04:20.760 --> 04:22.650
We really do our best to provide you with

04:22.650 --> 04:24.824
really good customer service here.

04:24.824 --> 04:27.480
And many of you have
known that our section

04:27.480 --> 04:29.429
has struggled with staffing shortages.

04:29.429 --> 04:34.230
And I wanted to take a moment
and say thank you to all the regions

04:34.230 --> 04:38.220
and let you know how much I've
appreciated you all's patience with us.

04:38.220 --> 04:40.409
It has been very challenging.

04:40.409 --> 04:43.800
We've recently added
some positions and our

04:43.800 --> 04:46.470
goal is to get you paid within 30 days.

04:46.800 --> 04:48.000
But I know.

04:48.000 --> 04:49.529
But wait, there's more.

04:49.560 --> 04:50.550
There's a caveat.

04:50.760 --> 04:53.670
We want to get you paid
but only if there's

04:53.670 --> 04:55.350
no additional information that's

04:55.350 --> 04:57.960
needed from either us on the payment side

04:58.410 --> 05:00.776
or on the contract manager's side.

05:00.776 --> 05:03.029
So, I hope that you're going
to find the information

05:03.029 --> 05:05.683
being presented today
will be helpful for you.

05:05.683 --> 05:09.760
I'm going to go ahead
and turn my camera off

05:10.540 --> 05:13.240
and we can go on to the next slide please.

05:14.540 --> 05:17.700
I'm going to do my best
here not to do deaf

05:17.700 --> 05:21.170
by PowerPoint and reading verbatim.

05:22.010 --> 05:28.880
But the slide here shows two types
of our RWP payment methods.

05:29.240 --> 05:32.195
We have the advanced method
which the grid applies here.

05:32.195 --> 05:33.900
And we have reimbursement.

05:33.900 --> 05:36.920
So, many of you received
or all of you should have

05:36.920 --> 05:38.960
received that are on the advanced method,

05:38.960 --> 05:42.700
your 20% of current
committed funds already.

05:42.700 --> 05:47.200
So, the highlight here, the first
20% that's what you've received.

05:47.200 --> 05:53.240
So, you may request your next
advance by providing basically

05:53.240 --> 05:57.980
90% of eligible expenses of
the previous advanced amount.

05:58.370 --> 06:00.800
And as the grid shows as we progress up to

06:00.800 --> 06:05.240
that 95% threshold of the committed funds.

06:05.240 --> 06:08.900
And as you continue to
submit eligible expenses,

06:08.900 --> 06:12.920
we withhold that last 5%
until project completion.

06:12.920 --> 06:15.950
So, reimbursement method,
very straightforward.

06:16.279 --> 06:20.390
You submit your eligible
expenses and we withhold 5%

06:20.390 --> 06:23.678
from each payment request
upon project completion.

06:23.678 --> 06:27.710
And with that I just wanted to
also mention that I know that

06:27.710 --> 06:31.355
you all that are on
the advanced method of payment,

06:31.355 --> 06:34.580
you are depositing into
a separate interest bearing

06:34.580 --> 06:37.760
account as it states in your contract.

06:38.390 --> 06:43.585
And with that, I will go ahead
and hand over the next slide to Ron.

06:43.585 --> 06:44.487
RON ELLIS: Alright.

06:44.487 --> 06:46.516
Thanks, Lisa.

06:46.516 --> 06:51.950
So, our payment request
submission guidelines here.

06:51.950 --> 06:55.610
According to Article One,
Section five of your contract,

06:55.610 --> 06:58.460
the payment request schedule is quarterly.

06:58.460 --> 07:02.540
So, this is something that
we're going to be asking

07:02.540 --> 07:05.630
you to be more vigilant
about this planning cycle.

07:05.630 --> 07:12.200
In past cycles it hasn't been
adhered to very closely sometimes.

07:12.590 --> 07:15.590
And it can be more difficult for everyone,

07:15.590 --> 07:19.310
for you all in for us to
process payments when

07:19.310 --> 07:23.900
a long period of time has
passed since the billable

07:23.900 --> 07:26.940
action or since the last payment request.

07:26.940 --> 07:32.870
Please note that if you're on
the advanced method you can submit

07:32.870 --> 07:36.530
requests before you've spent
90% of your previous advance.

07:36.530 --> 07:41.060
So, if you've accumulated some invoices

07:41.630 --> 07:44.210
but you haven't reached
the 90% threshold yet,

07:45.020 --> 07:48.170
you can go ahead
and submit a payment request.

07:48.830 --> 07:50.690
We'll keep track of your progress towards

07:50.690 --> 07:52.940
the next advance and we'll remit

07:52.940 --> 07:57.700
it to you when you've submitted
enough eligible expenses to qualify.

07:57.700 --> 08:01.250
So, when submitting a payment request,

08:01.250 --> 08:04.925
please submit it to invoice
at twdb.texas.gov.

08:04.925 --> 08:08.630
And please include the contract number

08:08.630 --> 08:10.805
in the subject line of your email.

08:10.805 --> 08:13.790
And please copy your contract manager.

08:13.790 --> 08:19.625
So, the Payment Request Form
is an Excel spreadsheet.

08:19.625 --> 08:25.400
And it has tabs on that spreadsheet
for the invoice ledger,

08:25.400 --> 08:27.870
the task ledger and the summary table.

08:27.870 --> 08:33.410
So, please save it along with
the invoices and support

08:33.410 --> 08:38.840
documentation as a PDF
and submit it as a PDF please.

08:39.170 --> 08:44.780
But please submit the progress
report as a separate PDF.

08:44.780 --> 08:49.324
We'll talk about the progress
report later in the presentation.

08:49.324 --> 08:53.072
And we'll talk about
the Payment Request Form,

08:53.072 --> 08:55.206
Lisa will on the next slide.

08:56.123 --> 08:57.040
LISA FARRELL: Thanks, Ron.

08:58.360 --> 09:01.540
Payment Request Form, I know a lot
of you are familiar with this.

09:01.840 --> 09:03.820
Down at the bottom I want to just go ahead

09:03.820 --> 09:05.889
and point this out first thing.

09:05.889 --> 09:08.785
We do have a link to our external website.

09:08.785 --> 09:13.630
And you can download the form but
I would like to encourage you to reach

09:13.630 --> 09:19.700
out to me directly if you would
like a worksheet sent to you.

09:19.720 --> 09:21.085
I have the setup.

09:21.085 --> 09:22.750
You've got my email address.

09:22.750 --> 09:26.184
I believe the contact information
was on the previous slide.

09:26.184 --> 09:28.780
But we will provide that for you.

09:28.780 --> 09:33.719
But I do encourage you, email me with
your contract number and just say,

09:33.719 --> 09:38.200
I'd like to get a worksheet and
I will get that over to you ASAP.

09:38.710 --> 09:39.510
Thanks so much.

09:39.510 --> 09:41.650
So, on the Payment Request Form.

09:41.650 --> 09:43.569
If you're using the advanced method.

09:43.569 --> 09:47.740
So, the next obvious payment
request would be payment number

09:47.740 --> 09:52.052
two because we have already
advanced you that first 20% So,

09:52.052 --> 09:54.340
if you're on the reimbursement method,

09:54.340 --> 09:56.755
of course your payment
requests will be number one.

09:56.755 --> 10:00.610
So, here highlighted, I want
to make a distinction between

10:00.610 --> 10:04.240
your submission schedule
versus the billing period.

10:04.240 --> 10:06.520
The billing period is going
to be your actual date range.

10:06.520 --> 10:09.160
And that includes your expenses,

10:09.160 --> 10:12.010
your subcontractors
and the sub subs as well.

10:12.010 --> 10:17.410
So, again, in the past a lot of
folks have sent in their payment

10:17.410 --> 10:22.990
request form with the date
reflecting the submission schedule.

10:23.500 --> 10:25.390
This billing period, this payment request

10:25.390 --> 10:27.610
form needs to cover that date range

10:27.610 --> 10:30.429
of actual work done
and what you're submitting

10:30.429 --> 10:32.530
for that particular packet.

10:32.530 --> 10:36.082
Requested amount obviously
will be advanced method.

10:36.082 --> 10:36.634
Sorry.

10:36.634 --> 10:41.110
The advanced method will be
the 20% of current committed funds.

10:41.110 --> 10:45.250
You will also be listing your interest

10:45.250 --> 10:47.949
earned on this payment request form.

10:47.949 --> 10:51.040
And for reimbursement it's the amount of

10:51.040 --> 10:53.259
eligible expenses minus your retainage.

10:53.259 --> 10:56.982
And please remember to sign
and date before submitting.

10:56.982 --> 11:00.348
Electronic signature is perfect.

11:00.348 --> 11:04.559
Next slide please.

11:04.559 --> 11:09.830
So, invoice/expense and task ledgers.

11:09.830 --> 11:14.650
So, we do ask you to provide
the breakdown amounts that's according

11:14.650 --> 11:19.270
to what your categories are from
exhibit b of your contract.

11:19.660 --> 11:22.929
Obviously, the task is what's being
done, explains how it's done.

11:23.890 --> 11:28.165
We need consistency with
your documentation.

11:28.165 --> 11:30.295
With your payment request form.

11:30.295 --> 11:34.630
Total amount of expenses
needs to add up with both

11:34.630 --> 11:37.120
your invoice and your task ledger please.

11:38.030 --> 11:42.910
And next slide we'll have
an example of the invoice ledger.

11:42.910 --> 11:48.679
As you can see we've got
the planning group information here.

11:48.740 --> 11:52.820
Currently you have those
particular budget categories,

11:52.820 --> 11:55.189
other expenses and voting member travel.

11:55.189 --> 11:58.861
We need to have underneath
that your subcontractor.

11:58.861 --> 12:04.520
Invoice is broken out by the executed
categories that are provided.

12:04.820 --> 12:07.580
If you notice that there's
a little sub sub there,

12:07.610 --> 12:09.920
a lot of the subcontractors
have their sub subs.

12:10.190 --> 12:12.990
Those can get wrapped
up into one line item.

12:12.990 --> 12:15.860
But again, we do need to
have this broken out.

12:15.860 --> 12:18.679
We need to make sure that all
expenses are consistent,

12:18.679 --> 12:21.770
the amounts are consistent and that we do

12:21.770 --> 12:24.020
have those budget categories allocated.

12:24.320 --> 12:27.570
Just a word of know, what
we have found previously.

12:27.590 --> 12:30.305
Sometimes there's a penny off on your

12:30.305 --> 12:32.975
subcontractor just heads up on that.

12:32.975 --> 12:36.485
TWDB, we cannot change
that amount for you.

12:36.485 --> 12:39.300
So, that may get kicked back to you.

12:39.300 --> 12:41.675
So, just be aware of that.

12:41.675 --> 12:43.700
When they're giving you
their breakdown make

12:43.700 --> 12:47.015
sure it adds up tasks
and expenses for them.

12:47.015 --> 12:52.429
So, that will cause a boomerang
effect unfortunately.

12:52.429 --> 12:56.920
And moving on to required
support documentation.

12:56.920 --> 12:59.940
I'm going to be referring
you for the next slide

13:00.570 --> 13:03.480
article for compensation or reimbursement.

13:03.480 --> 13:05.010
Please get familiar with this.

13:05.429 --> 13:07.650
This does provide additional information.

13:08.700 --> 13:12.300
We must have invoices
and support documentation from

13:12.300 --> 13:17.349
not only you the subcontractor
and also the sub-sub.

13:17.349 --> 13:19.757
We do ask for labor summary.

13:19.757 --> 13:25.480
It could be your employee
classification rate, number of hours.

13:25.480 --> 13:28.230
I've really appreciated last cycle.

13:28.230 --> 13:30.330
I did not get detailed timesheets.

13:30.330 --> 13:31.880
Thank you so much for that.

13:31.880 --> 13:35.160
We just need the summary which
most of the subcontractors

13:35.160 --> 13:38.220
will provide that in their
invoicing which is great.

13:39.210 --> 13:42.750
We must have again, those
categories broken out.

13:43.410 --> 13:47.700
And just a note here for
the regions, tear sheets or affidavits.

13:48.120 --> 13:51.450
The publications that come out
in the newspapers or online.

13:51.750 --> 13:59.250
We do need to see an invoice and
a proof that the publication did run.

14:01.559 --> 14:03.660
And on the next slide.

14:03.660 --> 14:07.140
I always like to highlight travel.

14:07.140 --> 14:11.670
We all know that state of
Texas is very transparent

14:11.670 --> 14:14.760
when it comes to travel
expense and reimbursement.

14:15.179 --> 14:18.277
We definitely want to
see backup for travel

14:18.277 --> 14:21.330
expense also for other categories as well.

14:21.810 --> 14:25.290
But specifically on the travel
expense, I want to emphasize that

14:25.290 --> 14:30.585
itemized meal receipts are
required and requested by TWDB.

14:30.585 --> 14:35.550
Mileage documentation can include
Google Maps or odometer readings.

14:35.550 --> 14:40.460
And now we're going to look
at the task ledger example.

14:40.460 --> 14:46.650
So, for this one here, I am asking
that when you fill out your task

14:46.650 --> 14:55.240
ledger that if you have several
different invoices that come in.

14:55.600 --> 15:00.430
I have had the task numbers listed several

15:00.430 --> 15:02.740
times and with different amounts.

15:02.740 --> 15:05.770
What we're asking is that
you roll everything up into

15:05.770 --> 15:08.470
one line item for that
particular task number.

15:08.470 --> 15:11.980
So, if you could just
list the task number once

15:12.250 --> 15:14.645
with the total task's cumulative amount.

15:14.645 --> 15:16.910
It is very much appreciated.

15:16.910 --> 15:24.760
And on the next slide, I'm happy to
say that with subcontractor proof

15:24.760 --> 15:29.800
of payment it's not required
to be included in your packet.

15:30.190 --> 15:34.660
It's already stated in
the contract that you are to pay

15:34.660 --> 15:37.880
your subcontractor before
submitting for reimbursement.

15:37.880 --> 15:41.530
So, this section right
here is no longer needed.

15:41.530 --> 15:44.200
But you are when you send in your packet,

15:44.200 --> 15:47.610
you have already paid your subcontractor.

15:47.610 --> 15:53.530
So, that is one of those small
benefits that's going to

15:53.650 --> 15:56.110
little bit less time
and processing these packets.

15:59.130 --> 16:03.810
And I'm going to hand over
the next slide to Ron.

16:03.810 --> 16:06.816
RON ELLIS: Thank you, Lisa.

16:06.816 --> 16:10.280
So, I'm going to talk a little
bit about the summary table.

16:10.790 --> 16:13.820
This may be a new item for some regions.

16:14.600 --> 16:18.410
Some of you all have been
submitting a table like this

16:18.740 --> 16:22.220
already with your payment
requests in previous cycles.

16:22.640 --> 16:24.500
And it's been very helpful.

16:24.500 --> 16:28.880
So, it tracks the percent of funds that's

16:28.880 --> 16:31.430
remaining in each task budget category.

16:32.300 --> 16:38.090
This can be very helpful
in foreseeing potential

16:38.090 --> 16:40.640
budget overages before they occur.

16:42.350 --> 16:45.680
It is the last tab on
the Payment Request Form.

16:45.680 --> 16:48.200
We've put a little spreadsheet in there

16:48.200 --> 16:52.580
for you that has each of the current

16:53.120 --> 17:01.307
tasks identified so that you can use
that as a template to submit this.

17:01.307 --> 17:08.770
So, that's the summary table requirements
and the point is to identify

17:08.770 --> 17:12.310
the percent and the cost of
each task that's completed.

17:14.119 --> 17:15.423
Progress reports.

17:15.423 --> 17:20.570
So, according to the planning
contract, you must include a progress

17:20.570 --> 17:24.980
report by task item since
the last progress report.

17:24.980 --> 17:29.900
You have to identify any problems
encountered and describe

17:29.900 --> 17:33.836
any actions taken to remedy the problems.

17:33.836 --> 17:39.590
So, as contract managers will be
comparing the progress report to

17:39.590 --> 17:43.820
the tasks that are being billed to
ensure that they're consistent.

17:45.020 --> 17:46.760
And as I requested before,

17:46.790 --> 17:52.946
please submit the progress
report as a separate PDF.

17:52.946 --> 17:59.230
So, we'll talk a little bit in the next

17:59.230 --> 18:02.380
couple of slides about some contract

18:02.380 --> 18:06.280
requirements that are in Exhibit B which

18:06.280 --> 18:10.139
is your task and expense budgets.

18:10.139 --> 18:13.060
So, reimbursement amounts for voting

18:13.060 --> 18:16.119
member travel is limited by statute.

18:16.119 --> 18:19.060
They the are same amounts as for state

18:19.060 --> 18:21.280
employees when state employees travel.

18:21.280 --> 18:26.890
So, the eligibility of
the expenses is limited by TWDB rules.

18:29.210 --> 18:31.490
Planning group members
can be paid for mileage

18:31.490 --> 18:33.860
to attend planning group meetings.

18:33.860 --> 18:42.214
Or in rare occasions they can be
paid for legislatively or TWDB

18:42.214 --> 18:45.400
board requested meetings for
traveled and those meetings.

18:45.400 --> 18:52.150
So, in the latter case which
is designated by to be here,

18:52.150 --> 18:56.250
the reimbursement has to be
specifically authorized by

18:56.250 --> 18:59.823
the planning group and by
the Water Development Board.

18:59.823 --> 19:06.353
So, a note regarding the certification
by the member that's required

19:06.353 --> 19:15.260
in 2A says that it cannot be
reimbursed by any other entity,

19:15.260 --> 19:18.800
political subdivision, etc, as
certified by the voting member.

19:18.800 --> 19:22.850
So, the planning group member must
certify that the mileage expenses

19:23.660 --> 19:27.240
can't be reimbursed by another
entity such as their employer.

19:27.240 --> 19:31.340
So, I know that some planning
groups have a form that

19:31.340 --> 19:34.625
they use for this mileage
and member certification.

19:34.625 --> 19:35.990
And that's great.

19:36.950 --> 19:39.320
Or the member can provide a letter.

19:40.100 --> 19:44.090
In either case, please include
that certification as part

19:44.090 --> 19:46.730
of the backup documentation
with your payment request.

19:47.570 --> 19:50.840
If your region doesn't have
a form and you'd like one,

19:50.840 --> 19:54.370
we can probably share that with you.

19:54.370 --> 19:57.296
So, just reach out and let us know.

19:57.296 --> 20:02.297
So, for planning group sponsor expenses.

20:02.297 --> 20:09.880
So, currently, political subdivisions
can only bill to task 10 in

20:09.880 --> 20:14.590
the task budget and to other
expenses in the expense budget.

20:15.430 --> 20:20.410
However, a new expense item
for salary and wages will

20:20.410 --> 20:23.520
be created in the upcoming
contract amendments.

20:23.520 --> 20:29.619
So, that expense category will be
where to charge personnel costs.

20:29.619 --> 20:35.122
So, this text here at the bottom
is, again is from Exhibit B.

20:35.122 --> 20:39.663
There are five types of costs,
letters A through E which

20:39.663 --> 20:43.210
includes several examples
of eligible direct costs.

20:43.210 --> 20:46.839
They're related to notice in meetings.

20:46.839 --> 20:52.150
Section E which is here
is just one subsection in

20:52.150 --> 20:54.587
the eligible expenses that
we wanted to highlight.

20:54.587 --> 20:56.830
We are highlighting it to make sure we

20:56.830 --> 20:58.570
point out that the personnel costs are

20:58.570 --> 21:02.050
very limited to staff
hours spent preparing

21:02.050 --> 21:04.075
for planning group meetings only.

21:04.075 --> 21:08.890
And also note that
they're capped at $5,000

21:08.890 --> 21:16.016
per regular meeting for a total
of $60,000, whichever is lower.

21:16.016 --> 21:17.833
Alright.

21:17.833 --> 21:23.034
Again, from Exhibit B
and eligible expenses.

21:23.034 --> 21:29.369
So, in addition to this list,
expenses that are identified

21:29.369 --> 21:32.045
in the regional water planning rules,

21:32.045 --> 21:36.200
Section 355.92A are ineligible.

21:36.200 --> 21:42.030
In the rules their activities where your

21:42.840 --> 21:45.869
existing information already exists or

21:45.869 --> 21:48.630
activities related to
preparation of regulatory

21:48.630 --> 21:51.180
permits that are ineligible.

21:52.970 --> 21:56.060
On the previous slide, we mentioned
that the sponsors personnel

21:56.060 --> 22:01.086
costs are limited to work related
to planning group meetings.

22:01.086 --> 22:05.730
Costs of administering
the grant are also ineligible.

22:05.730 --> 22:11.400
So, if you also made
an expense that's ineligible

22:11.460 --> 22:13.260
on something from this list,

22:14.460 --> 22:18.480
you'll get a letter with an adjusted
amount to the payment request

22:18.810 --> 22:22.290
and an attached worksheet
with a detailed explanation.

22:23.220 --> 22:29.250
If you submit appropriate
documentation for a denied expense,

22:30.119 --> 22:33.100
you can resubmit it with the next request.

22:33.100 --> 22:37.320
So, once the payment
requests had been approved

22:37.320 --> 22:38.640
by the contract manager and sent

22:38.640 --> 22:40.740
to finance for processing you'll get

22:40.740 --> 22:42.869
a Payment Request Report for review.

22:43.320 --> 22:48.629
And that can be helpful in making
sure that your numbers match ours.

22:48.629 --> 22:50.669
OK.

22:50.669 --> 22:55.709
So, certification of
administrative expenses.

22:55.709 --> 23:00.240
You all have begun doing this cycle
and you're doing a great job.

23:00.240 --> 23:02.685
So, this is a requirement.

23:02.685 --> 23:06.862
Again, in our rules, it's in 355.92C.

23:06.862 --> 23:10.260
The planning group must certify during

23:10.260 --> 23:12.210
a public meeting that the expenses

23:13.340 --> 23:16.550
are eligible for reimbursement
and are correct and necessary.

23:16.550 --> 23:19.500
So, planning groups can
make this certification

23:19.500 --> 23:22.530
for each invoice that you
approve payment for.

23:22.530 --> 23:26.340
Or you can do a blanket certification that

23:26.340 --> 23:27.740
can cover the whole planning cycle.

23:27.740 --> 23:30.690
So, in either case, it's important to

23:30.690 --> 23:32.820
include the date of the certification

23:32.820 --> 23:40.526
action by the planning group under
task 10 in the progress report.

23:40.526 --> 23:45.472
So, budget modifications.

23:45.472 --> 23:54.028
Again, this is in your contract,
Article Four, Paragraph E.

23:54.028 --> 23:58.480
As in past contracts,
exceeding a budget category

23:58.810 --> 24:01.300
by more than 35% requires a budget

24:01.300 --> 24:03.760
memo approved by the planning group

24:03.760 --> 24:06.650
and the TWDB Executive Administrator.

24:06.650 --> 24:10.300
So, if you see this coming,

24:11.530 --> 24:16.750
please reach out and we'll
work with you on a budget memo

24:16.750 --> 24:26.440
to adjust your task expense budgets to do

24:26.440 --> 24:28.300
a budget memo to make an adjustment.

24:28.300 --> 24:35.260
If you exceed in an expense request or in

24:35.260 --> 24:38.920
a payment request then we're going to have

24:38.920 --> 24:40.270
to kick that back to you and we're going

24:40.270 --> 24:41.855
to have to do the budget memo again.

24:41.855 --> 24:48.540
So, it's good to try to foresee this
and make adjustments in advance.

24:50.520 --> 24:56.180
Another note is that we will require

24:56.180 --> 24:58.100
you to provide a written explanation

24:58.100 --> 25:02.922
for the overage and reallocation
of the task and expense amount.

25:02.922 --> 25:04.685
Alright.

25:04.685 --> 25:08.210
So, subcontracts.

25:08.330 --> 25:12.050
This is unfortunately been
a point of confusion and we'll try

25:12.050 --> 25:16.195
to add some clarity and try to
get this good going forward.

25:16.195 --> 25:19.640
So, each subcontract
and subcontract amendment

25:19.880 --> 25:21.140
between the planning groups,

25:21.140 --> 25:23.780
political subdivision
and the primary technical

25:23.780 --> 25:26.270
consultant must be submitted

25:26.630 --> 25:30.249
to the Water Development Board for
official review and acceptance.

25:30.249 --> 25:33.470
Upon execution these documents should be

25:33.470 --> 25:37.360
sent to contracts at twdb.texas.gov.

25:37.360 --> 25:44.840
Again, please ensure to copy
your planner and include

25:44.840 --> 25:47.690
the contract number in
the email subject line.

25:49.280 --> 25:52.550
Please include that contract
member on the email subject line

25:52.550 --> 25:56.179
on any current or any
correspondence to the contracts,

25:56.179 --> 26:00.083
email box or to
the invoice email box please.

26:00.083 --> 26:04.310
The subcontract between
the political subdivision

26:04.310 --> 26:08.000
and the primary consultant
should specify the names of

26:08.000 --> 26:14.127
any sub-sub contractors
and the total sub-sub contract

26:14.127 --> 26:17.534
amount allocated to each
sub-sub contractor.

26:17.534 --> 26:20.869
So, this can be added
or revised and future

26:20.869 --> 26:22.520
sub-contract amendment if needed.

26:23.240 --> 26:27.350
But this is needed before
Water Development Board can

26:27.350 --> 26:30.546
provide payment for any
sub-subcontractor work.

26:30.546 --> 26:33.640
So, subcontracts must
include the provisions

26:33.640 --> 26:37.340
and clauses that are in Article Six,

26:37.340 --> 26:39.830
subcontracts of the prime contract.

26:39.830 --> 26:45.310
This last point here is one
that's been a stumbling

26:45.310 --> 26:48.209
block sometimes for planning groups,

26:48.209 --> 26:53.530
is that all of those provisions
and clauses the required provisions

26:53.740 --> 26:59.200
that are in Article Six are not
adopted in the subcontract.

26:59.200 --> 27:02.834
So, please be aware of that.

27:02.834 --> 27:07.507
Continuing subcontracts and middle.

27:07.507 --> 27:16.560
So, we'll review and if it's correct
we'll accept the subcontracts.

27:16.560 --> 27:22.109
But the sub-sub contracts
will no longer be

27:23.160 --> 27:27.340
reviewed and officially accepted by TWDB.

27:27.340 --> 27:31.010
So, that is a change from last cycle.

27:32.030 --> 27:35.313
Please continue to submit
those sub subcontracts

27:35.313 --> 27:39.935
and sub-sub contract
amendments to your planner.

27:39.935 --> 27:43.160
And we will keep them for
our records but they're not

27:43.160 --> 27:45.740
going to require official
review and acceptance.

27:46.280 --> 27:49.550
And another change is there
is not a certificate

27:49.550 --> 27:51.710
of procurement form associated

27:52.400 --> 27:57.697
with the 2026 original water
plan with our contract process.

27:57.697 --> 27:58.575
LISA FARRELL: Hey, Ron.

27:58.575 --> 28:02.279
if I can just kind of pipe in
here for just a second here.

28:02.279 --> 28:04.800
I just like to emphasize
on the payment side.

28:04.800 --> 28:09.270
When we're processing your
payments, when we have amendments

28:09.270 --> 28:11.970
that are increasing
your contracted amount,

28:11.970 --> 28:16.300
please make sure that you get
us your amended subcontracts.

28:16.300 --> 28:19.980
That is very critical because
we've had timing issues

28:19.980 --> 28:23.880
where we've received invoices
in and unfortunately

28:23.880 --> 28:26.250
budgets have been kind
of blown out because

28:26.250 --> 28:28.180
we didn't receive the amended subcontract.

28:28.180 --> 28:29.910
So, just keep that in mind.

28:29.910 --> 28:34.640
If your funds increase,
please get us your amended

28:34.640 --> 28:37.460
subcontracts so that those
get increased as well.

28:37.470 --> 28:40.530
And that way we can kind
of keep the process going

28:40.530 --> 28:44.973
and get you paid as soon as
we can get those through.

28:44.973 --> 28:46.027
Thanks.

28:46.027 --> 28:49.188
RON ELLIS: Thank you, Lisa.

28:49.188 --> 28:50.242
OK.

28:50.242 --> 28:55.090
So, we have contract amendments coming up.

28:55.090 --> 29:01.140
So, we've begun working on
the materials for these amendments.

29:02.250 --> 29:05.670
Those amendments will incorporate the full

29:05.670 --> 29:09.735
contract funding amount for each region,

29:09.735 --> 29:15.015
the full scope of work
and updated contract guidance,

29:15.015 --> 29:18.630
updated Exhibit C and Exhibit D.

29:18.630 --> 29:22.140
As I mentioned before, excuse me.

29:22.140 --> 29:26.190
As I mentioned before, the new
expense budget category for

29:26.190 --> 29:29.880
salaries and wages will be
included in this amendment.

29:29.880 --> 29:41.680
We plan to take the amendments to
our board for approval from them

29:41.680 --> 29:44.980
to authorize and execute
the contract amendments this summer.

29:46.930 --> 29:49.440
Last cycle, I don't
know if you recall this

29:49.440 --> 29:52.170
but you had to submit
a second funding application.

29:52.180 --> 29:55.510
We are not going to need
to do that this cycle.

29:55.510 --> 29:57.070
It'll just be a standard amendment.

29:57.460 --> 30:00.673
There will not be a new
funding application.

30:00.673 --> 30:06.450
So, that is the extent
of our presentation.

30:06.450 --> 30:09.920
Does anybody have any questions?

30:17.270 --> 30:18.405
Any comments?

30:18.405 --> 30:20.237
SPEAKER: I have a question.

30:20.237 --> 30:23.640
I'm coming from Rio Grande
Council of Governments.

30:24.840 --> 30:27.300
The progress report, is that just for

30:27.300 --> 30:34.065
the planning or is it
for the subcontractor?

30:34.065 --> 30:37.280
RON ELLIS: The it can be for both.

30:37.280 --> 30:37.600
Yes.

30:37.600 --> 30:43.876
But the subcontractor can submit
a progress report to the contractor

30:43.876 --> 30:50.140
or to the prime contractor and you
can submit both of those to us.

30:50.740 --> 30:51.797
It's very helpful.

30:51.797 --> 30:54.793
SPEAKER: You want that in our separate PDF.

30:54.793 --> 30:55.225
Right.

30:55.225 --> 30:56.227
RON ELLIS: Yes, please.

30:56.227 --> 30:56.798
SPEAKER: OK.

30:56.798 --> 30:57.370
Perfect.

30:57.380 --> 30:59.935
Thank you.

30:59.935 --> 31:03.570
CAMERON TURNER: Ron, I don't have any questions.

31:03.570 --> 31:05.610
Just some basic comments.

31:05.610 --> 31:09.750
First and foremost, I want to thank
you and Lisa for holding this

31:09.750 --> 31:13.460
together but also I want to thank
everybody for taking the time.

31:13.710 --> 31:16.080
I think this regional
water planning process,

31:16.290 --> 31:20.940
this grant program is
some of our most mature

31:21.840 --> 31:25.950
contracting processes within the board.

31:26.670 --> 31:29.880
And I think the sponsors
and the folks with all

31:29.880 --> 31:31.500
the entities you're working with and those

31:31.500 --> 31:35.790
of you on the line do
a great job of working to

31:35.790 --> 31:37.810
make sure that we're checking those boxes.

31:37.810 --> 31:41.934
Really the whole presentation
I think could be summed up though.

31:41.934 --> 31:42.186
Right.

31:42.186 --> 31:46.200
Like read your contract, be proactive
and talk to your contract manager.

31:46.920 --> 31:48.695
Ask questions if you got questions.

31:48.695 --> 31:51.780
You know, that especially
gets more important as we

31:51.780 --> 31:55.470
work through and get further
along in that process.

31:55.470 --> 31:55.830
Right.

31:55.830 --> 31:58.290
But like if we lay
the groundwork now and we get

31:58.290 --> 32:00.630
it right from the start then we have less

32:00.630 --> 32:03.120
of those problems
and corrections to make on

32:03.120 --> 32:05.969
the back end when it comes to close out.

32:05.969 --> 32:09.720
So, again, I just want
to say thank you all.

32:09.720 --> 32:13.510
And I do encourage anyone
and everyone to ask questions.

32:13.510 --> 32:17.500
Like I said, a lot of y'all have
been doing this for a while.

32:17.500 --> 32:17.700
Right.

32:17.700 --> 32:20.940
Like we've got a lot of repeat
customers here in the contracting

32:20.940 --> 32:23.580
process with this program
since it's a mature program.

32:23.580 --> 32:27.990
But that said, there could be some
new folks out there that are new to

32:27.990 --> 32:29.820
the process that can learn from those

32:30.420 --> 32:32.257
best practices and lessons learned.

32:32.257 --> 32:37.020
So, I encourage you all to have
just somewhat of an informal

32:37.020 --> 32:40.905
discussion here to share some
of those tips and tricks.

32:40.905 --> 32:43.320
RON ELLIS: Thank you, Cameron.

32:43.430 --> 32:44.970
I appreciate your comments.

32:48.260 --> 32:48.990
Yes.

32:48.990 --> 32:55.190
Sara just put a comment that we
will post the slides and we will

32:55.190 --> 32:59.590
post the recording of this for
future reference for you all.

32:59.590 --> 33:05.396
So, we'll go ahead and wrap up
if there's no additional questions.

33:05.396 --> 33:08.310
SPEAKER: I have a question?

33:08.310 --> 33:09.360
RON ELLIS: Oh, yes.

33:09.360 --> 33:09.810
Please.

33:09.810 --> 33:15.435
SPEAKER: Where it talks about when you do
the labor expense for the meetings.

33:15.435 --> 33:19.770
It says a total of 10%
of the total study cost.

33:19.770 --> 33:23.100
Is that what's allocated
to me as the political

33:23.100 --> 33:28.090
sub or is that the total contract cost?

33:28.090 --> 33:33.790
RON ELLIS: It's what's allocated to you.

33:33.800 --> 33:35.483
It's the contract cost.

33:35.483 --> 33:35.967
Yes.

33:35.967 --> 33:36.451
SPEAKER: OK.

33:36.451 --> 33:41.235
So, that doesn't include 10%
of what the consultants have?

33:41.235 --> 33:43.710
RON ELLIS: No, it does.

33:43.720 --> 33:48.585
It's 10% total but yeah.

33:48.585 --> 33:54.200
So, it's 10% of the total cost including

33:54.200 --> 33:58.930
what's allocated to the sub contract.

33:58.930 --> 33:59.784
SPEAKER: OK.

33:59.784 --> 34:00.638
OK.

34:00.638 --> 34:02.214
Thank you.

34:02.214 --> 34:03.791
RON ELLIS: You're welcome.

34:03.791 --> 34:05.095
Alright.

34:05.095 --> 34:07.270
Any more questions?

34:11.340 --> 34:13.590
Thank you all very much
for your time today.

34:14.730 --> 34:17.780
And again, any questions, any follow-up.

34:17.780 --> 34:21.810
Please reach out to your planner or to me

34:22.110 --> 34:25.650
or to the contracting staff directly.

34:29.260 --> 34:32.700
We're all trying to make
this the best process

34:32.700 --> 34:36.530
and get you all paid as
quickly as possible.

34:36.530 --> 34:39.990
So, I think we all have the same goal here

34:39.990 --> 34:42.030
and we work together it'll to work out.

34:43.110 --> 34:44.040
Thanks again.

34:44.040 --> 34:46.265
And I hope you all have a great day.

34:46.265 --> 34:47.708
LISA FARRELL: Thank you.

34:47.708 --> 34:48.776
SPEAKER: Thank you.

34:48.776 --> 34:49.804
SPEAKER: Thank you.

34:49.804 --> 34:50.658
CAMERON TURNER: Thank you.

34:50.658 --> 34:51.338
SPEAKER: Thank you.

34:51.338 --> 34:51.980
SPEAKER: Thank you.